The Management Board for the Bac Lieu Wind Power Plant said, after nearly three months connecting to the national grid, the Bac Lieu Wind Power Plant with 10 wind turbines has supplied 3 million KWh of electricity, meeting the target. The Electricity of Vietnam (EVN) signed a contract to buy electricity from the facility.
Currently, 52 remaining turbines of the plant are being erected and expected to be completed and put into operate in late December 2014.